CONSTRUCTION UPDATES
We’ve been working hard on construction since late last fall and are excited about the progress. With the rain behind us, we are working on formwork and installing rebar for the Land Park Underpass Widening over I-5, grading on the trail alignment between Riverside Blvd and Sutterville Road and demolishing the existing Willow Slough railroad bridge. These are on track to be completed by mid May.
The City will keep you updated through e-newsletters and signage in addition to updating this website and please note some dates may shift due to weather conditions. The general contractor is Mountain Methods Inc. and the project is being completed under City Project No. K15165100 and Federal Aid Project No. ATPL-5002(189).
Sign up for email notifications if you haven’t received email communications about Del Rio Trail in the past.
For more information, please call 916-491-3161 or email [email protected].